Purchaser Information
Stay up-to-date with the progress of your land, and access all the documents and guidelines you and your builder will need throughout your home building journey at Creekstone.
Find your stage
Northern Precinct
Stage N04
Electrical install complete. Concrete paths 40% complete
complete - 70%EST. titles due
Q4 2024
Northern Precinct
Stage N06
Works Complete. Awaiting Council agreement on external infrastructure
complete - 100%EST. titles due
October/November 2024
Northern Precinct
Stage N05
Complete
100%Titles Received
8th january 2024
Settlements Commenced
22nd january 2024
Stage W25
Complete
100%TITLES RECEIVED
21st november 2023
Settlements Commenced
5th december 2023
Northern Precinct
Stage N03
Complete
100%TITLES RECEIVED
17TH OCTOBER 2023
Settlements Commenced
31ST OCTOBER 2023
Northern Precinct
Stage N02
Complete
100%Titles Received
29th August 2023
Settlements Commenced
12th September 2023
Northern Precinct
Stage N01
Complete
100%Titles Received
13th July 2023
Settlements Commenced
27th July 2023
Stage 22
Complete
100%Titles Received
11th October 2022
Settlements Commenced
25th October 2022
Stage 21
Complete
100%Titles Received
19th September 2022
Settlements Commenced
3rd October 2022
Stage 23
Complete
100%Titles Received
24th August 2022
Settlements Commenced
6th September 2022
Stage 5L
Complete
100%